Activity: Monitor Project Status
Capture Work Status
In this step, the project manager captures primitive metrics on the progress of project work and product quality. The methods to be used to capture these metrics are described in the project's Measurement Plan. Typically, project team members submit regular progress reports to the project manager providing the following information:
For more information on metrics, see Guidelines: Metrics. Derive progress indicators
In order to properly assess the project's progress in relation to the plans, the project manager "rolls-up" the primitive metrics reported by the project team to provide a full picture of the project's progress. The project's Measurement Plan describes how these derived metrics (the "progress indicators") are calculated. Derive quality indicators
In addition to monitoring the work progress, the project manager also monitors the quality of the project artifacts. Quality metrics (again as defined by the project's Measurement Plan), are consolidated to provide an overall picture of the project's status compared to its stated quality objectives. Evaluate indicators vs. plans
Having derived the project's progress and quality indicators, the project manager compares these against the expected state of the project as defined by the Software Development Plan and Iteration Plans. At this point the project manager will evaluate the following:
The project manager will also review the risk indicators identified for each risk on the Risk List to decide whether any risk mitigation strategies should be activated at this time. Any issues that have been reported are captured on the project's Issues List (which will be reported in the Status Assessment). Issues that fall within the project manager's authority should be resolved directly, as part of Activity: Handle Exceptions and Problems. Issues arising that require escalation to the Project Review Authority are
included in the Status Assessment and forwarded to the PRA for resolution. Often
this is done during the PRA Project Review activity. |