- 10.3 Reviewing a task when it is underway
-
- If a task is underway and the work done so far has been recorded
- then there is an option which will assist with the recalculation of
- the tasks schedule. The "Review calculation" menu option on the
- "Task" menu allows the end, work or rate, as indicated by the
- "End/work/rate" menu option to be re-estimated. It is similar to
- using the enter key to change the current task details which also
- recalculates the tasks schedule. The difference is that this option
- allows the work done so far to be taken into consideration.
-
- The dialog which appears when selecting this option will show the
- work planned and the work done for comparison, along with the date
- the work done was recorded up to. These values may not be changed
- here. It is important for the calculation that the work done and
- date are accurate, failing to do this will result in incorrectly
- recalculated values. The remaining options which may be updated on
- the review calculation dialog depend upon what value is being
- calculated:
-
- End The remaining work and resource work rates are
- displayed. The remaining work shows how much work
- is left to do to complete the task (equals work
- planned minus the work done). The remaining work
- rates are initially set to be equal to the current
- planned work rates. Updating either the remaining
- work and/or rates will set the work equal to the
- work done plus the remaining work, will
- recalculate the end of the task and will set the
- resource rates for the task to be the average work
- rates taking into account the start, and newly
- calculated end and total planned work values.
-
- Work The end date and remaining work rates are
- displayed. The remaining work rates are initially
- set to the current planned work rates. Updating
- either the end date and/or rates will set the work
- equal to the work done plus the calculated
- remaining work and will set the resource rates to
- be the average work rate taking into account the
- start, end and newly calculated planned work. The
- remaining work is calculated by looking at the
- duration between the date indicated as being when
- the work done was recorded up to and the end date,
- taking into account the remaining work rates.
-
- Rate The remaining work and end date are displayed. The
- remaining work shows how much work is left to do
- to complete the task (equals work planned minus
- the work done). Updating either the remaining work
- and/or end will set the work equal to the work
- done plus the remaining work and will set the
- resource rates appropriately.
-
- 11. MEMOS
-
- A memo, or Psion Word document may be associated with each task. To
- create a new memo select the "Edit memo" menu option from the "Task"
- menu. This will activate the Psion Word Application. Enter the memo
- and exit Word to return to Plan. Once a memo has been created a memo
- symbol will appear next to the description for the task in the task
- list view. To subsequently view or edit the memo use the "Edit memo"
- option.
-
- To remove a memo use the "Delete memo" menu option.
-
- Memos are stored in a sub-directory below the directory in which the
- plan file is stored. The sub-directory will have the same name as
- the plan file. Each memo will be stored as a separate Word file
- within the sub-directory. Memo filenames are constructed using the
- task Id and therefore task Id's should be restricted to valid
- filenames.
-
- If a plan file is deleted, moved or renamed, remember to update any
- sub-directory which contains memo files, otherwise Plan will not be
- able to find the memos.
-
- 12. RESOURCES
-
- Plan allows any number of resources to be created, subject to Psion
- memory limitations. The work hours for each day of the week are
- stored in the form of start and end times. There is also a three
- year calendar which indicates the resources holidays or non-work
- days.
-
- By default when first using Plan only one resource will be available
- called "General". This will be constructed using the following
- rules:
-
- - The current year is used as the start of the three year
- calendar period.
- - The work/non-work days for the three year calendar are set
- according to the work days which have been set in the Psion Time
- application.
- - The start and end time for each work day will default to 9:00am
- and 5:00pm respectively.
-
- When creating additional resources the work hours and holiday
- settings are copied from the "General" resource. Consequently it
- will save time by setting common work hours and public holidays in
- the "General" resource before creating any additional resources.
-
- The holidays set for the "General" resource should be common public
- or bank holidays. Changing the holidays for the "General" resource
- will update the equivalent days for all other existing resources,
- e.g. if 25 December is changed to a holiday then all other resources
- will be updated to ensure that the 25 December is also a holiday.
- Individual resource holidays may subsequently be overridden on a
- resource by resource basis.
-
- To create a new resource use the "Make" menu option from the
- "Resource" menu. This will prompt for a resource name which must be
- unique. To delete a resource select the "Kill" menu option. This
- will display a dialog prompting for the name of the resource to
- delete. Any existing tasks which use the resource will then be
- switched to use the "General" resource.
-
- There is a concept of a current resource in the same way that there
- is a current task. The current resource is the resource which is
- displayed in the resource usage and holiday views. To change the
- current resource use the "Switch to" menu option on the "Resource"
- menu, or press the tab or shift-tab key to cycle through the
- available resources in the resource based views.
-
- 13. PREFERENCES
-
- The following preferences may be set using the "Preferences" menu
- item on the "Special" menu:
-
- PERT chart
-
- Task top text None, Description, Start, End, Work, Rate,
- Resource, Done, Labour, Fixed, Total, Value, Text,
- Saved Start, Saved End, Saved Work, Dependencies
-
- Task bottom text None, Description, Start, End, Work, Rate,
- Resource, Done, Labour, Fixed, Total, Value, Text,
- Saved Start, Saved End, Saved Work, Dependencies
-
- Gantt chart
-
- Task bar text None, Description, Start, End, Work, Rate,
- Resource, Done, Labour, Fixed, Total, Value, Text,
- Saved Start, Saved End, Saved Work, Dependencies
-
- Holiday shading Use general, Resource specific
-
- Shading control None, Day zoom, Week zoom, Month zoom
-
- Saved start/end bar Yes, No
-
- Calculation
-
- New tasks End, Work, Rate
-
- Recalculation Automatic or Manual
-
- Display
-
- Dates/times Dates & times, Dates only
-
- Grey graphics Yes, No
-
- Resources
-
- Average work day Time in hours and minutes
-
- The PERT chart task top and bottom text options control which items
- appear above and below the task boxes in the PERT chart.
-
- The Gantt chart task bar text controls what is displayed at the end
- of each task bar in the Gantt chart.
-
- The Gantt holiday shading option controls the shading of holidays in
- the Gantt chart. If set to "Resource specific" any non-working days
- will be shaded grey for the particular resource the task is
- allocated to. The "General" resource will be used if multiple
- resources are assigned to one task. If set to "Use general" then all
- shading will use the holidays for the "General" resource. The later
- option will result in much faster redraws of the Gantt chart.
-
- Note that shading can be time consuming when zoomed out, hence the
- "Shading control" option allows it to be turned on at suitable
- scales.
-
- The Gantt chart saved start/end bar option controls whether one or
- two bars are used for each task in the Gantt chart. If one bar is
- used (the "No" option) then the bar indicates the start and end of
- the task. If two bars are used (the "Yes" option) then a lower bar
- is also displayed which indicates the equivalent dates from the
- saved start and end fields. This is useful for seeing how the
- current plan compares with the original estimates.
-
- The new task calculation item controls whether for new tasks the
- end, work or rate of work is calculated. For existing tasks this may
- be controlled individually using the "End/work/rate" menu option.
-
- If the recalculation option is set to automatic then if any task
- changes any tasks which are dependent upon the task will also be
- recalculated. This implies that it should never be necessary to
- force a recalculation unless resource details change. When set to
- manual only the task which is edited will be recalculated, in this
- case the tab key or "Recalculate all" menu option should be used to
- recalculate all tasks when required. Note that the critical path is
- not automatically updated even if the calculation option is set to
- automatic. The "Recalculate all" or the "Critical path" menu options
- should be used to update the critical path when required.
-
- The dates/times preference setting controls whether times are
- entered and displayed. If it is set to "Dates & times" then start
- and end dates will include a time component. If the setting is
- "Dates only" then start and end dates will have no time component.
-
- The grey graphics option controls whether a grey plane is used
- within Plan. This provides an enhanced display at the expense of an
- extra 10K of memory.
-
- The average work day option defines the duration of one normal work
- day. This unit of work is used when entering work and work done
- values. Typically this should be set to the length of an average
- working day, including any breaks.
-
- The preference settings are saved in the plan and resource file and
- so will be restored the next time the files are opened by Plan.
-
- 14. PRINTING
-
- The task list may be printed using the print options available on
- the "File" menu from the task list view. The output from the print
- option is sent to the device specified using the "Printer" menu
- option accessed from the "Control" menu on the Psion system screen.
- This may be set to use a printer attached to the serial or parallel
- port or a file. If the given destination is not ready, e.g. a serial
- cable is not connected then an error message will be displayed.
-
- The print output may also be sent through a PC to an attached
- printer via Psion's PsiWin software. Note that PsiWin is a Psion
- software product and is not supplied with Plan.
-
- The "Print Setup" menu option on the "File" menu controls the paper
- size, orientation, printer type, etc. This option also provides
- control over the range of fields or columns which are to be printed
- from the task list and the width of the description and user text
- fields. Where the specified printer cannot handle the printing of
- all the fields from the task list across the page it will be
- necessary to use the print option more than once with a different
- range of fields each time. The task Id and description fields are
- always printed on the left of the page, the range of fields printed
- on the right may be specified.
-
- The "Print preview" menu option may be used to take a look at the
- overall page layout prior to printing.
-
- There is an optional postscript printer module for printing the
- Gantt and PERT charts (see "Modules" section).
-
- 15. MODULES
-
- A number of plug in modules are available with Plan. These modules
- consist of files with an OPO file extension which are located in a
- sub-directory called PLAN below the directory where the main
- PLAN.OPA file is kept. When these modules are available the "Run
- module" menu option on the "Special" menu will display the
- additional facilities supplied by the optional modules. Each Plan
- module will appear as a separate item within the modules dialog. To
- access a module select the corresponding item in the run module
- dialog.
-
- The currently available modules are:
-
- MPX.OPO Allows data to be transferred between the Psion
- Plan application and Microsoft Project 3.0 and
- 4.0.
-
- PS.OPO Provides a postscript print facility for the Gantt
- and PERT charts.
-
- AGN.OPO Allows tasks to be exported to a Psion Agenda
- file.
-
- 15.1 Microsoft Project MPX module
-
- The MPX module allows task and resource data to be exchanged with
- Microsoft Project 3.0 and 4.0. To transfer data into Microsoft
- Project:
-
- - Ensure that the MPX.OPO module is installed in a directory
- called \APP\PLAN on any drive.
- - Ensure the plan to be transferred is open.
- - Select the "MPX transfer" option from the "Run module" menu
- item.
- - Select "Export".
- - Enter the name of the MPX export file which is to be created.
- - The file will be generated.
- - Transfer the MPX file to the relevant host machine.
- - Start up Microsoft Project and select the open file option.
- Choose the MPX 1.0, 3.0 or 4.0 file type rather than the Project
- file type (it does not matter which version of MPX file is used).
- - If asked whether the file should be merged into the current
- project choose "No". It is not possible to merge a plan into an
- existing Microsoft Project plan.
-
- To transfer a project from Microsoft Project into Psion Plan:
-
- - Save the file as an MPX file (any version) and transfer it to
- the Psion.
- - Create a new Psion plan and resource file. The data may be
- merged into an existing plan and resource file provided the incoming
- task Id and resource initials are equivalent to any old ones.
- - Select the "MPX transfer" option in Plan.
- - Choose "Import".
- - Select the MPX import file which is to be read.
- - The file will now be read. Look for any warning or error
- messages in the output. Press any key when complete to continue in
- Plan.
-
- Note the following points before attempting to import data into
- Plan:
-
- - Plan expects numbers to be in a given format, as specified by
- the "Number formats" menu option on the "Control" menu of the Psion
- system screen. For example, if you have a German version of
- Microsoft Project then in general numbers will include a comma for a
- decimal point rather than a dot. The number format settings on the
- Psion should match the international settings on the PC before
- exporting/importing MPX files.
- - Avoid modifying the standard Export tables in Microsoft
- Project.
- - Plan expects a date format of the form "31/12/95", "31/12/95
- 12:33am" or "31/12/95 12:33". The date order is not important, e.g.
- 92/12/31 may also be used. Ensure the date format is set correctly
- in Microsoft Project preferences before creating the MPX file. In MS
- Project 4.0 the date format may be set as above from the "Options"
- menu item on the "Tools" menu and in the "View" section.
- - Plan uses the resource initials field for the resource name,
- these should be set in Microsoft Project.
- - Plan ignores dependencies of the type Finish-Finish and Start-
- Finish.
- - Plan assumes a holiday lasts all day so avoid holidays which
- are less than a full day in Microsoft Project.
-
- 15.2 Postscript module
-
- The postscript module may be used to print the Gantt or PERT chart
- on a postscript printer. Selecting the print postscript menu option
- from the "Run module" dialog will display a dialog which controls
- which chart to print along with the page size and orientation.
-
- The output from the postscript module will be sent to the device
- specified using the "Printer" menu option on the "Control" menu on
- the Psion system screen. If the given destination is not ready, e.g.
- a serial cable is not connected then an error message will be
- displayed.
-
- The custom width and height apply only if the page size is set to
- "Custom". These give the smallest and largest measurements
- respectively of the paper in centimetres. The margin item controls
- the width of the margin around the edge of the paper.
-
- When printing the Gantt chart a second dialog will appear which
- allows the date range to be specified. This may be set to either the
- entire project, derived from the current Gantt view, the remaining
- part of the project, or a specified date range. The custom start and
- end dates are used only when the range item is set to "custom
- dates". The Gantt chart will be paginated if necessary, the PERT
- chart will always be printed on one page.
-
- When printing the PERT chart a second dialog will appear which
- allows a section of the PERT chart to be printed. If set to "All"
- then all the PERT chart will be printed on one sheet of paper. If
- set to "Pert view" then the top left corner of the printout will
- match the top left corner of the current view in the PERT chart. In
- this case the "Pert view screens" option controls the amount to be
- printed, a value of 1 implies that the printout will correspond to
- the PERT chart.
-
- Note that printouts may be sent to a printer connected to a PC via
- the RPRINT utility and a 3Link cable. RPRINT is included in the
- freely available RCOM package developed by Psion which is also
- supplied with PsiWin.
-
- Users without access to a postscript compatible printer may like to
- investigate the facilities available with the software called
- Ghostscript. This allows postscript output to be viewed and printed
- on most printers connected to a PC. Aladdin Ghostscript and a front-
- end called Ghostview may be obtained via the Internet from
- ftp.cs.wisc.edu in the directory /pub/ghost.
-
- 15.3 Agenda module
-
- The Agenda module provides a mechanism for transferring task details
- to the Psion Agenda application. Plan will create a new agenda file
- which contains a dated to-do entry for each task in the current open
- plan. The due date of each to-do item will be the end date for the
- corresponding task. The start date of the task will be used as the
- date from which the to-do will be displayed in the day/week view of
- Agenda. The interface also provides a facility to set an alarm for
- each to-do entry which will activate at the given time on the end
- date for the task.
-
- Once the agenda file has been created there are two possible
- techniques for using the file:
-
- - Maintain the file as a separate Agenda file and open it as a
- separate Agenda process.
- - Merge the file into an existing Agenda file.
-
- 16. COMMAND SUMMARY
-
- Menu Name Key Purpose
-
- File New psion-n Create new plan file
- Open psion-o Open existing plan file
- Save as psion-a Save plan under a new name or
- save plan as a text file (comma
- separated, tab separated or
- space padded)
- Save psion-s Save plan and resource file
- Revert psion-v Revert plan and resource files
- to last saved versions
- Print setup psion-y Print configuration (paper
- size, orientation, printer,...)
- Print preview psion-* Preview output from print
- option
- Print psion-p Print task list to the serial
- or parallel port or a file. Use
- the system screen printer
- control option to set-up the
- print destination and
- parameters
- Edit Copy psion-c Copy current task into a buffer
- Insert psion-i Re-insert task from buffer
- Delete psion-J Delete current task (see also
- Delete key)
- Edit memo psion-M Create or edit memo associated
- with current task
- Delete memo psion-D Delete memo associated with
- current task
- Task End/work/rate psion-r Change current task calculation
- to end, work or rate
- Dependencies psion-d Change current task
- dependencies
- Cost & data psion-b Change cost and user data
- Set work done psion-W Enter/update work done field
- for current task
- Review psion-R Re-estimate end/work/rate for
- calculation current task taking into
- consideration work done so far
- and remaining work
- Pert Move psion-A Move current task in PERT chart
- dynamically using cursor keys,
- any key exits mode
- Pert X/Y psion-Y Set current tasks x, y PERT
- position
- Resource Make psion-m Make a new resource
- Kill psion-k Delete a resource
- Switch to psion-w Change current resource and
- display resource histogram
- display
- Rename psion-j Rename a resource
- Settings psion-u Set current resource maximum
- units, charge rate and work
- hours.
- Over- psion-L Checks for cases where
- allocated? resources have been allocated
- too much work. Displays tasks
- associated with over-allocated
- resources
- Holiday count psion-h Count non-public holidays
- between two dates for current
- resource
- Start year psion-K Set year for start of three
- holiday calendar for all
- resources
- Plan Set fields psion-E Set saved fields or set user
- text field to a W.B.S
- identifier
- Critical Path psion-/ Recalculate critical path
- Recalculate psion- Force recalculation of tasks
- all minus (see also tab)
- Totals psion-e Calculate and display summary
- of totals for current plan
- (work planned, done, % done,
- start and end dates, costs)
- View Zoom font in psion-z Alter size of font
- Zoom font out psion-Z Alter size of font
- Zoom in psion-z Change scale on time axis
- Zoom out psion-Z Change scale on time axis
- Field order psion-t Customise order of fields in
- task list view
- Mask tasks psion-B Controls which tasks are
- visible in Task list, Gantt and
- PERT charts
- Sort tasks psion-S Sort tasks
- Layout PERT psion-l Automatically layout tasks in
- PERT chart
- Refresh psion-F Refresh screen
- Cursor off psion-C Turn cursor off until any key
- pressed (useful in combination
- with psion-control-shift-s
- which saves current screen to a
- file)
- Special Preferences psion-q Set preferences
- Find text psion-f Find given text in task id,
- description or user text fields
- Find again psion-g Find next occurrence of text
- About Plan psion-V Display information about Plan.
- Register psion-Q Register Plan using a
- registration key.
- Run module psion- Run optional Plan module
- plus
- Exit psion-x Exit Plan
- Diamond Task view psion-N Switch to task view
- Task list psion-T Switch to task list view
- Gantt chart psion-G Switch to Gantt chart view
- PERT chart psion-P Switch to PERT chart view
- Resource usage psion-U Switch to resource usage view
- Holidays psion-H Switch to holiday view
- (Keys) Tab Force recalculation of all
- tasks
- Enter Edit current task details
- Shift- Insert a new task above current
- Enter task
- Delete Delete current task
- Help On-line help system
- Space Re-centre Gantt or PERT display
- on current task
- Esc Abort recalculate all
-
- 17. HISTORY
-
- Version (Date) Notes
-
- 1.0.1 (May. `94) Restricted alpha 1 release for evaluation
- purposes only.
-
- 1.1.1 (July `94) Restricted alpha 2 release for evaluation
- purposes only.
- Minor bug fix to dependency dialog.
-
- 1.2.1 (Sep. `94) Restricted alpha 3 release for evaluation
- purposes only.
- Added critical path option.
- Enhanced PERT task display to allow text above and
- below task boxes to be set independently. Also added
- resource, rate and status to list of options for PERT
- task texts.
- Adjusted positioning of tasks with auto PERT layout
- and position of texts above task boxes.
- Increased maximum number of tasks from 74 to 99.
- Increased maximum x-shift on PERT chart.
-
- 1.3.1 (Sep. `94) Bug fix to zoom option in Gantt view when using
- new project.
- Changed duration to work.
- Made building of default calendar faster.
- Added optional modules menu.
- Created MPX transfer module.
-
- 2.0.2 (Oct. `94) First public release.
- Change in file formats.
- Added extra task fields for work done, costs and user
- data.
- Renamed some of the menus and rearranged some of the
- menu key activation's.
- Added recalculation and tracking options.
- Amended MPX module to work with extra fields.
- Added border to all views.
- Changed print option to use system screen print set-
- up.
- Added shareware registration.
-
- 2.1.2 (Nov. `94) Minor bug-fix, check for \PLN directory failed.
-
- 2.2.2 (Jan. `95) Added options to shade holidays in Gantt chart,
- (enabled from the preferences setting).
- Milestones now drawn differently in Gantt chart.
- Shift-diamond works in opposite direction to diamond
- key.
- Refresh can now be interrupted by diamond key.
- Tasks can now be sorted by a number of fields.
- New postscript printer module.
- New module providing interface to Agenda.
- A few other minor changes.
- Fixed a few bugs.
-
- 3.0.3 (Mar. `95) Major new release.
- File formats changed.
- Maximum number of tasks increased to 200 from 99.
- Description field length increased from 30 to 255.
- Maximum number of dependencies per task increased from
- 4 to 8.
- Added summary/outline tasks.
- 4 font sizes now available using standard psion-z
- keys.
- PERT chart now zoomable and with vertical scroll.
- Added extensive on-line help.
- Speed of core algorithm improved.
- Speed of holiday shading in Gantt chart improved.
- Added facility to allow field order in task list to be
- user definable.
- Memos may be associated with each task.
- Added support for 24 hour time format.
- Added code to get around OPL limit on long choice
- lists when have many tasks and resources.
- Menus are now view sensitive, i.e. inappropriate
- options do not appear.
- Added support for 8 character currency symbols.
- Added option for year symbol in Agenda interface.
- Agenda interface now creates a named to-do list.
- Various minor enhancements and bug-fixes.
-
- 3.1.3 (Aug `95) Added mask option to control which tasks are
- shown (mask by level, resource, date,...).
- Option to display a task field at the end of each task
- bar in the Gantt chart.
- Sort tasks by Id field.
- More information in plan totals display.
- Updating general holidays affects holidays for all
- other resources.
- Added option to count a resources holidays between 2
- dates.
- Some changes to MPX module to better support MS
- Project 4.0 and German MPX file format.
- Now looks for registration file, plan.reg, on disks
- A:, B: and M:.
- Displays date at top of holiday view.
- Option to specify project specific or common resource
- file when creating a new project.
- Bug fix so that if update task doesn't delete any
- attached memos.
- Bug fix to postscript print module so that uses
- correct shading when printing full project.
- A few other minor changes.
-
- 3.2.4 (Oct `95) Added resource maximum units data.
- Option to find over-allocated resources.
- Added saved start, end and work fields so that the
- latest dates can be compared with the initial
- settings.
- New "Set fields" menu option to set saved fields or to
- set user text field to a W.B.S identifier.
- New mask options on start and end date field mask
- which compares fields to saved fields.
- New find option.
- Implemented proper Psion print setup, print preview
- and print options for task list. Previous print
- options are now available under the menu option "Save
- as".
- New preference option which controls whether dates and
- times are used or just dates.
- Menus reorganised to be more consistent with other
- Psion applications and make room for more options.
- Tab and shift-tab can now be used in holiday and usage
- views to cycle through resources.
- Pressing space in Gantt and PERT chart will alter zoom
- to display current task.
- CTRL-up and CTRL-down move to top/bottom of task list.
- Improved interrupt to refresh of screen on specific
- keys.
- Current view, task and resource is saved when the plan
- is saved.
- Save option now always saves, instead of saying the
- plan has not changed.
- Various improvements to MPX module.
- A few other minor enhancements and bug-fixes.
-
- 4.0 (Apr `96) Backed out some of the changes made to do with
- the dates/times preference setting to avoid rounding
- errors. This option now only affects the input/display
- of times not the internal calculation.
- Plan now uses an external message file so that it can
- be translated into a number of languages.
- Multiple resources may be assigned to one task.
- Grey plane option.
- Description and dependencies may now be shown in the
- Gantt and PERT charts.
- The print setup is now saved with the plan.
- Postscript output greatly improved.
- New Plan start up title screen.
- Mask sub-tasks option.
- Memory handling completely different, (now uses less
- memory for small plans).
- Completed tasks now crossed out in PERT chart.
- A few minor bug-fixes.
-
- 4.1 (Jul `96) A minor bug fix release.
-
-