SOPHISTICATED RESOURCE MANAGEMENT
Beware of project management software that claims to help you spot resource overloads and optimize resources. Independent testing shows that when using the identical data, the results of various project management software products vary by as much as 400%! If effective resource management is an important issue for you, make sure the project management software you are using or selecting allows for task splitting when analyzing resources. Without it, resource analysis generates nonsensical results. To understand the importance of task splitting in scheduling work to optimize resources, consider the following example....
A long task (A) has a duration of 12 days and 3 days of spare time or float (meaning the task can be delayed up to 3 days without delaying the project deadline). The task requires 1 resource (R). About half way through task A, task B (taking one day) must occur and it is on the critical path. Tasks C and D are dependent on B completing and are also on the critical path.
Tasks A and B cannot be scheduled at the same time because there is only one of resource R. How should resource R be scheduled in order to optimize the use of the resource and get the project done on the target date of day 15? Task A starts, but because most project management software cannot interrupt a task (task splitting), task B is delayed until the end of task A when the resource R is released from A to B. Consequently, the project is delayed 8 days! Microsoft Project© and AutoPlan© as well as most other popular products do not provide task splitting and will produce similar results.
Micro Planner solves this problem by interrupting task A for the one day required for task B. In the process, one day of A's float or spare time is used up. This task splitting capability allows the critical path tasks B, C and D to be scheduled on time. The project deadline is met without overloading the resource.
Of course, this is only four tasks and one resource. Micro Planner provides the same sophisticated resource analysis for thousands of tasks and hundreds of resources across multiple simultaneous projects. It can show you how to juggle tasks and resources to take advantage of pockets of extra time (float) and under-utilization of resources to boost productivity dramatically.
In addition to sophisticated task splitting, Micro Planner also provides: